Monday, February 6, 2012

We have walls!!

Well, not quite... but there are frames that are ready to be dry-walled.  Though I'm kind of sad that I will no longer be able to have superhero, walk through walls, power anymore!  The master bathroom and closet have been framed and the duct work has been re-configured.  Here is a picture of the walls as they look today:


Here's my painted up version, trying to show where the walls and doors will be:


So here's our to-do list as of today:

Jack up Floor
Reconfigure HVAC/Vents
Order windows
Order Vanity/Shower
Lights/Outlets/Plumbing
Drywall
Install Windows
Finish Drywall
Paint
Redo hardwood/Trim/Doors
Install Vanity/Shower/Mirror/Fixtures

We are behind on our original schedule so we're just taking it a week at a time now.  Jacking up the floor has proven to be a bigger pain than originally anticipated but it's getting done.  Wish us luck :)